Project Description
The project is to determine the feasibility of setting up 1000 MW power plant in Western Bangladesh and selling a portion of capacity in the local market based on the market need.
Overviewing different entities of the power sector and their roles (Specially REB), regulatory framework and impacts of relevant development.
Gathering information of the current physical system – existing generation capacity and existing transmission capacity
Assessing different aspects of the proposed addition like Generation – capacity, commissioning schedules (year-wise), location, ownership, fuel, likely pricing (fixed, variable, first year), sale arrangements, transmission – capacity and likely loading, tied capacity, likely pricing etc.
Assessing different market aspects like – Consumption pattern – West and East Bangladesh, Demand/Supply gap (region wise), Tariffs and realization, Collection efficiency of distribution companies and Transmission, Distribution & Commercial losses etc.
Conducting a feasibility study on various types on consumers and recommend the consumers for targeting.