top of page

Green Power Development and Energy Efficiency Improvement Investment Program

Client

Asian Development Bank (ADB)/ Government of Sri Lanka (Ceylon Electricity Board)

Sector

Energy & Power

Country

Sri Lanka

Timeline

2016- 2018

Project Description

Objective of procurement of consulting services was for Project Management Support For Tranche 2 Sub-Projects which included:


  1. Transmission projects

  2. Distribution project

  3. Demand Side Management projects covering smart grid, smart buildings and cold storage



Description of actual services provided by your staff within the assignment:


The Consultants’ scope of work covered two major areas:

  1. a) Transmission and Distribution Projects

(i) Evaluated and finalized the Tranche 2 transmission and distribution subprojects;

(ii) Carried out Environmental and Social Safeguard Assessment relevant to the


Tranche 2 transmission and distribution subprojects;

  1. b) Demand Side Management projects covering smart grid, smart buildings and cold storage

(i) Designed the smart grid pilot project under Tranche 1 with the

participation of the CEB Engineers.

(ii) Guided CEB to implement the smart grid pilot project by preparing specifications, request for proposals, selection of contractors, and ensuring the pilot project is implemented in accordance with the concept and the specifications

(iii) Designed the smart building pilot project under Tranche 1 with the participation of the CEB Engineers.

(iv) Guided CEB to implement the smart building pilot project by preparing specifications, request for proposals, selection of contractors, and ensuring the pilot project is implemented in accordance with the concept and the specifications

(v)  Designed the cold thermal storage pilot project under Tranche 1 with the participation of the CEB Engineers.

(vi)  Guided CEB to implement the cold thermal storage pilot project by preparing specifications, request for proposals, selection of contractors, and ensuring the pilot project is implemented in accordance with the concept and the specifications